|
Offshore
Riser Gantry Crane, Tube Handling Equipment from Geo Robson &
Co Ltd and RJD Engineering. Oil Exploration Equipment, Oil Rig and
Drilling Deck handling equipment.
|
|
|
|
|
|
Click
Here to return to News Page 
|
 |
Robson
Group Work Together To Secure Future Orders |
Riser
Gantry Crane for the Offshore Oil Exploration Industry |
Team
Effort Ensures Success |
 |
For the
past three months the skyline at Hellaby Industrial Estate has had
a new figure. Standing over 25metres tall the Riser Gantry Crane
has had a temporary home at RJD Engineering.
A joint
venture by Sheffield based Geo Robson & Co Ltd and its sister company
RJD Engineering
the Riser Gantry crane has been designed and built for the Oil Exploration
Industry.
The final
destination is the offshore Oil Rig, Olinda Star, Brazil. The contract
totalling £1 million was awarded to Robson from Shipley based TSC
Offshore,
formally Patriot Mechanical Handling who not only designed the Crane
but also the King Post Deck Cranes, BOP Handling, and Tree Handling
Systems totalling $20million for the refurbishment of the Olinda
Star.
The crane
was pre-built at Hellaby, Rotherham, to enable the hydraulic and
electrical systems to be fully tested and proved. The large sections
weighing as much as 65 Tonnes, proved to be a very complex lift,
the whole structure weighing in at a mighty 125 tonnes.
|
click pictures to enlarge

Left: David
Oliver
Centre: Dave Parker
Right: Robert Guest
|
 |
 |
 |
Four
huge mobile cranes had to be used to ensure the lift went without
a hitch, with one goliath 500 ton, two 200 ton and one 75 ton cranes,
all on site at the same time, with only a few feet between them,
the Robson Site Manager Dave Parker stated, "Every move had to be
planned well in advance and calculated to the inch, following strict
health and safety procedures to ensure the safety of everyone on
site".
The
lift involved the central bridge section being lifted to 30m high
to enable the side legs to be lifted and manoeuvred under the bridge
and the bridge lowered on to the top. A cherry picker was used to
reach the high connections and enable the fixing of the connecting
bolts.
|

Teamwork
Keeping
Everyone Safe
|
 |
 |
 |
RJD
Engineering fabricated all of the structural sections and provided
all of the ancillary steelwork, utilising most of its 42,000 square
foot workshop. Robson provided the mechanical systems for the crane,
with all the electrical and hydraulic systems fitted in situ, the
engineers certainly needed to have a head for heights.
The
crane was dismantled this week ready for its long journey to Brazil,
an equally complex lift using the same combination of heavy lift
equipment, the cranes supplied by Ainscough
of Manchester. Jason Delvard of Ainscough,
said "It was a very difficult job, in a very tight space, the experience
of the crane drivers and slings men certainly shone through, with
everyone working very closely with the Robson and RJD team, made
sure that the job was safe and successful.
|
High Skills Needed in Such a Tight Space
|
 |
 |
 |
With
the cranes offshore destination the specification was very high,
with all the welds and connections having to undergo rigorous testing.
The documentation
and components all had to be completely traceable, Mike Howard,
Managing Director of RJD
Engineering, stated, "It was a huge challenge for all
of the team, the success of this build shows that Sheffield and
Rotherham still have some of the best engineering skills in the
world.
|

Gently
does it, its only 125 tonnes.
|
 |
 |
 |
The two
companies performance and professionalism impressed TSC
Offshore so much,
that a follow up order was placed for additional offshore equipment
and an enquiry for another Riser Gantry Crane to be built early
in the New Year.
|
|
 |
 |
Click
Here to return to News Page 
|
 |
|
|
|
|
|
|
|
|
|
|
|
Geo.
Robson & Co. (Conveyors) Ltd
Coleford Road, Sheffield, S9 5PA
|
|
|
Fax:
+44 (0)114 2433066
|
|
|